Free PMP Practice Questions – Agile based

With the new version of the PMP exam, Agile questions are up to 50%. Try these Agile based FREE PMP practice questions. Ten (10) questions to test your knowledge on the Agile content of the PMP exam while preparing for the exam.

These are questions composed by PMP certified Project professional; Ogaga Johnson.

PMP Practice Questions

  • Mandi is a project manager in a pharmaceutical company, she was assigned a new innovative project and is in the process of determining which project life cycle she would use for the project. Which of the following options should she choose?
    1. Predictive
    2. Iterative
    3. Hybrid
    4. Agile
  • You are working on estimating the duration on an agile project as a result, you decide to review previous sprints to determine on average, the number of story points the team can complete within each sprint. You are trying to determine the team’s?
    1. Speed
    2. Rate of progress
    3. Effort
    4. Velocity
  • In Agile projects, the role of a PM is replaced with that of a team facilitator. Which of the following are the responsibilities of the team facilitator? Select two options
    1. Manages the project team
    2. Removes impediments
    3. Selects the features to be worked on for each sprint
    4. Manages the scrum process
  • You are the scrum master on a software development project, the development team just concluded developing the features in the current sprint and are doing a demo to showcase the features developed. What sprint process are they performing?
    1. Daily stand up
    2. Review
    3. Retrospective
    4. Planning
  • Remi is a new hire and she got invited to a meeting where everyone is taking turns to say what they are working on this week, what they worked on last week and the problems they encountered. Remi comes to you to ask what the meeting was about, and you tell her you were having a?
    1. Daily stand up meeting
    2. Review meeting
    3. Retrospective meeting
    4. Planning meeting
  • You are a stakeholder on a project and you want to request for an ongoing sprint to be cancelled. Who should you approach to cancel the sprint?
    1. Product owner
    2. Team members
    3. Team facilitator
    4. Stakeholders
  • Bill is the PM on a project which uses an adaptive lifecycle. Bill notices that the team members have a board and they move features across the board as they progress. What type of adaptive approach are they using?
    1. Scrum
    2. Kanban
    3. Iterative based approach
    4. eXtreme Programming
  • Timi is used to the predictive lifecycle mindset, however, for his new project, his manager has asked him to adopt an agile mindset. Which of the following doesn’t represent such mindset?
    1. Individuals & Interactions
    2. Customer collaboration
    3. Working software
    4. Contract negotiation
  • A daily stand up meeting is typically used for? Select two options
    1. Status meetings
    2. Solving problems
    3. Uncovering problems
    4. Micro-commitment to each other
  • Susan is learning about the scrum methodology, which of the processes below is in the correct order?
    1. Sprint planning > Scrum meeting > Sprint retrospective > Sprint review
    2. Sprint review > Sprint planning > Scrum meeting > Sprint Retrospective
    3. Sprint planning > Scrum meeting > Sprint review > Sprint retrospective
    4. Scrum meeting > Sprint retrospective > Sprint review > Sprint planning

Find out about the new PMP exam content, new question types and what to expect.

Check if you got the answers correct

The correct answers are in bold and red

  • Mandi is a project manager in a pharmaceutical company, she was assigned a new innovative project and is in the process of determining which project life cycle she would use for the project. Which of the following options should she choose?
    1. Predictive
    2. Iterative
    3. Hybrid
    4. Agile
  • You are working on estimating the duration on an agile project as a result, you decide to review previous sprints to determine on average, the number of story points the team can complete within each sprint. You are trying to determine the team’s?
    1. Speed
    2. Rate of progress
    3. Effort
    4. Velocity
  • In Agile projects, the role of a PM is replaced with that of a team facilitator. Which of the following are the responsibilities of the team facilitator? Select two options
    1. Manages the project team
    2. Removes impediments
    3. Selects the features to be worked on for each sprint
    4. Manages the scrum process
  • You are the scrum master on a software development project, the development team just concluded developing the features in the current sprint and are doing a demo to showcase the features developed. What sprint process are they performing?
    1. Daily stand up
    2. Review
    3. Retrospective
    4. Planning
  • Remi is a new hire and she got invited to a meeting where everyone is taking turns to say what they are working on this week, what they worked on last week and the problems they encountered. Remi comes to you to ask what the meeting was about, and you tell her you were having a?
    1. Daily stand up meeting
    2. Review meeting
    3. Retrospective meeting
    4. Planning meeting
Need help with answering PMP exam questions? Check out: How to answer PMP practice exam questions
  • You are a stakeholder on a project and you want to request for an ongoing sprint to be cancelled. Who should you approach to cancel the sprint?
    1. Product owner
    2. Team members
    3. Team facilitator
    4. Stakeholders
  • Bill is the PM on a project which uses an adaptive lifecycle. Bill notices that the team members have a board and they move features across the board as they progress. What type of adaptive approach are they using?
    1. Scrum
    2. Kanban
    3. Iterative based approach
    4. eXtreme Programming
  • Timi is used to the predictive lifecycle mindset, however, for his new project, his manager has asked him to adopt an agile mindset. Which of the following doesn’t represent such mindset?
    1. Individuals & Interactions
    2. Customer collaboration
    3. Working software
    4. Contract negotiation
  • A daily stand up meeting is typically used for? Select two options
    1. Status meetings
    2. Solving problems
    3. Uncovering problems
    4. Micro-commitment to each other
  • Susan is learning about the scrum methodology, which of the processes below is in the correct order?
    1. Sprint planning > Scrum meeting > Sprint retrospective > Sprint review
    2. Sprint review > Sprint planning > Scrum meeting > Sprint Retrospective
    3. Sprint planning > Scrum meeting > Sprint review > Sprint retrospective
    4. Scrum meeting > Sprint retrospective > Sprint review > Sprint planning

How many correct answers did you get? tell me in the comment section and if you have any questions, please let me know.

Try out more PMP exam practice questions here.


Wondering how to pass the PMP Exam? Get my FREE PMP Exam Checklist. It contains the 6 powerful tips that I used to prepare, study and pass the PMP Exam with an above target in all domains at my first attempt. It has been updated to align with the new version of the PMP exam.



If you have any questions or contributions, please do so by leaving a comment in the comment section below.

If this was useful, please share this article with your network and on social media using the share buttons below.

10 thoughts on “Free PMP Practice Questions – Agile based”

  1. Chidinma Ikejiaku

    Hi Ogaga,

    This was interesting, 9 questions were gotten right. I did not get the last question( Scrum methodology process).

    Thank you.

  2. Hi Ogaga,
    Very interesting questions..
    I got 8 out of 10.
    I didn’t get nos 4 and 5.
    I am still confused on how to differentiate the meetings (daily stand-ups, reviews, retrospective, planning; which is which).
    I will read more on it..

    Thank you.
    Ihuoma.

    1. Hi Ihuoma, I published a blog post today explaining the different meetings. Check it out. Title is Scrum Overview.

Leave a Comment

Your email address will not be published. Required fields are marked *