Thanks for trying out the FREE PMP practice questions. The answers for the ten (10) questions are in “bold”. The rationale for the answer has also been included for each question.

The questions and answers were composed by PMP-certified Project professional; Ogaga Johnson.

Answers

Answer rationale: The team charter is most accurate because this document is specially created to establish the team operating guidelines.

For a breakdown of the above question and the answer, check out my post: How to answer PMP practice exam questions

Answer rationale: Withdraw is most correct because you are avoiding resolution at the moment and deferring it to a later time.
Answer rationale: According to the PMBOK 6th edition, the next process after Developing the project charter is the Identify stakeholders process
Answer rationale: Pull communication is best for communicating with a large audience. They can pull the information whenever they want. This way, people get the exact information they want eliminating the risk of them receiving irrelevant information. An example of pull communication is by using web portals. You have the project information/status update on the website and anyone interested goes to the website to get an update on the project.
Answer rationale: When CPI is less than 1, it means the project is spending more than the budget (over budget) and when CPI is greater than 1, it means that the project is spending less than the budget (under budget)
Answer rationale: Schedule crashing is a schedule compression technique that adds more resources on a project to speed up the project time. This results in high cost. If the customer is willing to add more funds, you can add more resources on the project to ensure it is completed on time.
Answer rationale: According to the PMBOK 6th edition, stakeholders with high power and low interest should be kept satisfied. Stakeholders with high power and high interest should be managed closely; stakeholders with low power and high interest should be kept informed; stakeholders with low power and low interest should be monitored.
Answer rationale: Project Scope Statement contains the project exclusions. Therefore, the best document to show is the Project Scope Statement because it would show that the feature was clearly among the project exclusions.
Answer rationale: VUCA is a predetermined list used in the identify risk process. Others include PESTLE and TECOP
Answer rationale: Single source is when there are other sellers that can provide what you want to buy, however, you prefer to work with a particular seller.

How did you do in this test? Share your result with me in the comment section.


Wondering how to pass the PMP Exam? Get my FREE PMP Exam Checklist. It contains the 6 powerful tips that I used to prepare, study and pass the PMP Exam with an above target in all domains at my first attempt.


If you have any questions or contributions, please do so by leaving a comment in the comment section below.

If this was useful, please share it with a PMP aspirant using the share buttons below.

9 Responses

  1. I got 9 out of 10. I missed out on the question about the stakeholder that was arguing about his/her requirement or feature that wasn’t included. I chose the requirements documentation but now I now understand.

    Thank you mama!

    1. Hi Ayomide, that’s a good score. Weldone.

      Yes, that question is quite tricky. Glad you understand it now. Thanks for your comment.

  2. I got 9 out of 10. I missed out on the question about the stakeholder that was arguing about his/her requirement or feature that wasn’t included. I chose the requirements documentation but now I now understand.

    Thank you mama!

    1. Hi Eremi, weldone. What you need to do now is to review the questions you failed. You could also read up on the processes/knowledge areas which you fail most questions on. This helps to close any knowledge gap you may have. Keep practicing!

    1. Hi Adenike, don’t be sad. The essence of these questions is to check areas where you need more knowledge on so that you close any knowledge gaps before the main exam :). So review the questions you failed and read up those knowledge areas or processes to ensure adequate understanding of the concept. If you haven’t you could also get PMP training/coaching courses to further help with understanding the PMP complex terms. Feel free to ask any question you may have. I’m rooting for you.

  3. I am wondering from answering for question 3. According to the PMBOK 6th edition, the next process should be Develop Project Management Plan

    1. According to the PMBOK 6th edition, the next process after Developing the project charter is the Identify stakeholders process. These are the two processes in the Initiation process group. The Develop Project Management Plan is the first process is the next process group which is the planning Process group.