Thanks for trying out the FREE PMP practice questions aligned with the new version of the PMP exam. The answers for the ten (10) questions are in “bold”. The rationale for the answer has also been included for each question.

The questions and answers were composed by PMP-certified Project professional; Ogaga Johnson.

Answers

Answer rationale: The question is asking for the document that contains information on the information needs of stakeholders: the information each person or group should receive, their information requirements, expectations including the level of detail, format, and content of the information. This information is contained in the Communication management plan.

Answer rationale: The iteration process is about repeating the development process until the product/result/service is correct (this development approach focuses on correctness). It delivers a single product/result/service.

Answer rationale: The daily scrum meeting or stand-up meeting is typically no longer than 15mins.

Answer rationale: Statistical sampling involves choosing part of a population of interest for inspection. The 1000 bottles produced should be the same, therefore, randomly pick a sample e.g 10% and inspect them to access the quality of the deliverable.

Answer rationale: Requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. This is used to track/trace where requirements are as they move through the phases.

Answer rationale: Negotiation is the preferred method for dispute resolution. Try negotiating first.

Answer rationale: The purpose of the bidders’ conference is to provide potential sellers with an understanding of the project requirements and ensure they have a clear understanding of the procurement request.

Answer rationale: The risk report provides summary information on identified project risks such as the number of threats and opportunities.

Answer rationale: Training and equipment are examples of preventive costs incurred due to the cost of quality. Testing is an example of appraisal cost and Rework is an example of failure cost.

Answer rationale: The product backlog and product roadmap are developed by the product owner. The Product owner is responsible for guiding the direction of the product

How did you do in this test? Share your result with me in the comment section.


Wondering how to pass the PMP Exam? Get my FREE PMP Exam Checklist. It contains the 6 powerful tips that I used to prepare, study and pass the PMP Exam with an above target in all domains at my first attempt. It has been updated to align with the new version of the PMP exam.



If you have any questions or contributions, please do so by leaving a comment in the comment section below.

If this was useful, please share this article with your network and on social media using the share buttons below.